The management team in the above problem assigns each goal a numerical value designating its importance. The "bulls eyes," circles and triangles are replaced by the values 3, 2 and 1 respectively…
The correct answer is F. Prioritization matrix. See the full explanation below for the reasoning.
Analyze Phase
Question
The management team in the above problem assigns each goal a numerical value designating its importance. The "bulls eyes," circles and triangles are replaced by the values 3, 2 and 1 respectively. Entries are made in each box by multiplying the 3, 2 or 1 by the goal value. The importance of each activity is calculated by adding the entries in its row.
Exhibit
Options
- AAffinity diagram
- BInter-relationship digraph
- CTree diagram
- DProcess decision program chart
- EMatrix diagram
- FPrioritization matrix
How the community answered
(32 responses)- B13% (4)
- C6% (2)
- D3% (1)
- E3% (1)
- F75% (24)