A team working with a plant relocation is tasked with designing a process for moving 180 pieces of equipment. Incoming orders may need to be filled during the move at either the old site or the new…
The correct answer is D. Process decision program chart. See the full explanation below for the reasoning.
Improve Phase
Question
A team working with a plant relocation is tasked with designing a process for moving 180 pieces of equipment. Incoming orders may need to be filled during the move at either the old site or the new one. Transportation equipment availability is uncertain. Construction schedules at the new site is very weather dependent. The team designs a chart that attempts to cover these and other contingencies with appropriate measures dealing with each. The tool best fitted for this task is:
Options
- AAffinity diagram
- BInter-relationship digraph
- CTree diagram
- DProcess decision program chart
- EMatrix diagram
- FPrioritization matrix
- GActivity network diagram
How the community answered
(25 responses)- A12% (3)
- B4% (1)
- D76% (19)
- F8% (2)
Topics
#PDPC#contingency planning#risk management#seven management tools