When management selects an approach or set of actions to align assessed risks with the organization's risk appetite in the context of strategy and objectives, this is called:
The correct answer is B. Risk Response. See the full explanation below for the reasoning.
Question
When management selects an approach or set of actions to align assessed risks with the organization's risk appetite in the context of strategy and objectives, this is called:
Options
- ARisk Assessment
- BRisk Response
- CRisk Analysis
- DInformation and Communication
- EMonitoring
How the community answered
(27 responses)- B78% (21)
- C4% (1)
- D11% (3)
- E7% (2)