Tracking the status of each requirement throughout the development and test phases is called:
The correct answer is D. Requirements Tracing. See the full explanation below for the reasoning.
Question
Tracking the status of each requirement throughout the development and test phases is called:
Options
- ARequirements Checking
- BRequirements Verification
- CIn-Process Review
- DRequirements Tracing
- EPhase-End Review
How the community answered
(26 responses)- A12% (3)
- B4% (1)
- C4% (1)
- D81% (21)