CSQA · Question #49

The team member is told what to do, and then how to check that what was done was done correctly. This statement shows relationship between:

The correct answer is C. Do and Check Processes. See the full explanation below for the reasoning.

Question

The team member is told what to do, and then how to check that what was done was done correctly. This statement shows relationship between:

Options

  • APlan and Do Processes
  • BPlan and Check Processes
  • CDo and Check Processes
  • DDo and Act Processes

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    10% (3)
  • C
    84% (26)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.