In the Cost of Quality diagram shown, the COQ cost labeled "A" represents:
The correct answer is B. Failure Costs. See the full explanation below for the reasoning.
Question
In the Cost of Quality diagram shown, the COQ cost labeled "A" represents:
Exhibit
Options
- APrevention Costs
- BFailure Costs
- CAppraisal Costs
- DCost of Production
How the community answered
(53 responses)- A6% (3)
- B79% (42)
- C11% (6)
- D4% (2)