CSQA · Question #438

Which of the following is not a process within Level 4 for maturing Quality Assurance Processes?

The correct answer is D. Process History Database. See the full explanation below for the reasoning.

Question

Which of the following is not a process within Level 4 for maturing Quality Assurance Processes?

Options

  • AProcesses Aligned to Objectives
  • BProcesses Integrated
  • CProcess Optimization
  • DProcess History Database

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    7% (3)
  • C
    18% (8)
  • D
    71% (32)

Community Discussion