CSQA · Question #426

Planning for system test process begins when:

The correct answer is C. At project start. See the full explanation below for the reasoning.

Question

Planning for system test process begins when:

Options

  • AAfter coding phase
  • BAt start of system testing phase
  • CAt project start
  • DAfter design phase

How the community answered

(42 responses)
  • A
    12% (5)
  • B
    2% (1)
  • C
    81% (34)
  • D
    5% (2)