Software
CSQA · Question #426
Planning for system test process begins when:
The correct answer is C. At project start. See the full explanation below for the reasoning.
Question
Planning for system test process begins when:
Options
- AAfter coding phase
- BAt start of system testing phase
- CAt project start
- DAfter design phase
How the community answered
(42 responses)- A12% (5)
- B2% (1)
- C81% (34)
- D5% (2)