Which management tool would you use if your QA team needed to prioritize issues?
The correct answer is C. Nominal Group Technique. See the full explanation below for the reasoning.
Question
Which management tool would you use if your QA team needed to prioritize issues?
Options
- ACause-and-Effect Diagram
- BAffinity Diagram
- CNominal Group Technique
- DForce Field Analysis
- EProcess Map
How the community answered
(60 responses)- A2% (1)
- B5% (3)
- C70% (42)
- D17% (10)
- E7% (4)
Community Discussion