The requirement for a control is:

The correct answer is B. A risk to be reduced. See the full explanation below for the reasoning.

Question

The requirement for a control is:

Options

  • ALimit individual's ability to perform
  • BA risk to be reduced
  • CIdentify individuals violating organizational rules
  • DHold individuals accountable for problems
  • EAssist management in accomplishing their mission

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    79% (22)
  • C
    7% (2)
  • E
    4% (1)