Before defining a new process, the scope of the process should be identified. Element(s) for process scope is(are):

The correct answer is D. High-Level Process Flow, Major Deliverables, and Stakeholders. See the full explanation below for the reasoning.

Question

Before defining a new process, the scope of the process should be identified. Element(s) for process scope is(are):

Options

  • AHigh-Level Process Flow
  • BMajor Deliverables and Stakeholders
  • CHigh-Level Process Flow and Major Deliverables
  • DHigh-Level Process Flow, Major Deliverables, and Stakeholders

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    14% (4)
  • C
    7% (2)
  • D
    76% (22)