Software
CSQA · Question #314
Before defining a new process, the scope of the process should be identified. Element(s) for process scope is(are):
The correct answer is D. High-Level Process Flow, Major Deliverables, and Stakeholders. See the full explanation below for the reasoning.
Question
Before defining a new process, the scope of the process should be identified. Element(s) for process scope is(are):
Options
- AHigh-Level Process Flow
- BMajor Deliverables and Stakeholders
- CHigh-Level Process Flow and Major Deliverables
- DHigh-Level Process Flow, Major Deliverables, and Stakeholders
How the community answered
(29 responses)- A3% (1)
- B14% (4)
- C7% (2)
- D76% (22)
Community Discussion