CSQA · Question #30

Which is generally considered the most important step in the process of contracting for software development?

The correct answer is A. Selecting an outside organization as a contractor. See the full explanation below for the reasoning.

Question

Which is generally considered the most important step in the process of contracting for software development?

Options

  • ASelecting an outside organization as a contractor
  • BContract negotiations
  • COperation for maintenance
  • DBudget Criteria

How the community answered

(34 responses)
  • A
    79% (27)
  • B
    6% (2)
  • C
    12% (4)
  • D
    3% (1)