Which of the following would be measured subjectively to develop a baseline:

The correct answer is C. Understandability of training material. See the full explanation below for the reasoning.

Question

Which of the following would be measured subjectively to develop a baseline:

Options

  • ANumber of people assigned a project
  • BProjects completed on schedule
  • CUnderstandability of training material
  • DLines of code

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    76% (37)
  • D
    14% (7)