Which of the following would be measured subjectively to develop a baseline:
The correct answer is C. Understandability of training material. See the full explanation below for the reasoning.
Question
Which of the following would be measured subjectively to develop a baseline:
Options
- ANumber of people assigned a project
- BProjects completed on schedule
- CUnderstandability of training material
- DLines of code
How the community answered
(49 responses)- A4% (2)
- B6% (3)
- C76% (37)
- D14% (7)