In the context of process maturity, 'check process continuum' moves from:

The correct answer is A. Literal Controls to Intent Controls. See the full explanation below for the reasoning.

Question

In the context of process maturity, 'check process continuum' moves from:

Options

  • ALiteral Controls to Intent Controls
  • BManagement Controls to Employee Controls
  • CIntent Controls to Literal Controls
  • DMinimal to Heavy Controls

How the community answered

(51 responses)
  • A
    75% (38)
  • B
    4% (2)
  • C
    16% (8)
  • D
    6% (3)