CSQA · Question #241
A common term that is used today for contracting for software development is "performance based contracting." Performance based contracting means:
The correct answer is B. The performance criteria for a contractor will be defined in the contract. See the full explanation below for the reasoning.
Question
A common term that is used today for contracting for software development is "performance based contracting." Performance based contracting means:
Options
- AThe previous performance of a contractor is a critical success factor
- BThe performance criteria for a contractor will be defined in the contract
- CThe performance of the software will be defined in the contract
- DThe contractor will receive a bonus if performance exceeds the contract provisions
How the community answered
(28 responses)- A7% (2)
- B79% (22)
- C4% (1)
- D11% (3)
Community Discussion
No community discussion yet for this question.