Using the PDCA Cycle concept, defining the mission of a Quality Assurance function would be considered which PDCA phase?

The correct answer is A. Plan. See the full explanation below for the reasoning.

Question

Using the PDCA Cycle concept, defining the mission of a Quality Assurance function would be considered which PDCA phase?

Options

  • APlan
  • BDo
  • CCheck
  • DAct

How the community answered

(54 responses)
  • A
    76% (41)
  • B
    6% (3)
  • C
    15% (8)
  • D
    4% (2)