CSQA · Question #213
In the context of the PDCA cycle, Work Processes represent the _____ component and the Check Processes represent the ___________component.
The correct answer is A. Do | Check. See the full explanation below for the reasoning.
Question
In the context of the PDCA cycle, Work Processes represent the _____ component and the Check Processes represent the ___________component.
Options
- ADo | Check
- BPlan | Do
- CAct | Check
- DDo | Act
How the community answered
(39 responses)- A82% (32)
- B3% (1)
- C5% (2)
- D10% (4)