Which one of the following is NOT one of the change control procedures?

The correct answer is D. Developer should provide access rights for the change in configuration management tool. See the full explanation below for the reasoning.

Question

Which one of the following is NOT one of the change control procedures?

Options

  • AProposed change should be formally approved
  • BDevelopers should make the program changes.
  • CAn independent person, other than the person who made the change, should test the final revised
  • DDeveloper should provide access rights for the change in configuration management tool.
  • EThe documentation system should be updated with all change sheets or change registers

How the community answered

(38 responses)
  • A
    16% (6)
  • B
    5% (2)
  • C
    5% (2)
  • D
    71% (27)
  • E
    3% (1)