Correlation between process maturity and an organization's willingness to embrace change can be described as:

The correct answer is B. Lags slightly at the lower levels and accelerates during the higher levels of maturity. See the full explanation below for the reasoning.

Question

Correlation between process maturity and an organization's willingness to embrace change can be described as:

Options

  • AAccelerates at the lower levels and lags during the higher levels of maturity
  • BLags slightly at the lower levels and accelerates during the higher levels of maturity
  • CAccelerates at same rate at all levels
  • DNone of the above

How the community answered

(55 responses)
  • A
    4% (2)
  • B
    73% (40)
  • C
    7% (4)
  • D
    16% (9)

Community Discussion