Why should senior leaders avoid promising exact delivery dates?
The correct answer is C. It creates false confidence. False certainty is more damaging than acknowledged uncertainty.
Agile Principles and Mindset
Question
Why should senior leaders avoid promising exact delivery dates?
Options
- ATeams might fail
- BMarkets change
- CIt creates false confidence
- DIt increases pressure
How the community answered
(35 responses)- A6% (2)
- B14% (5)
- C77% (27)
- D3% (1)
Explanation
False certainty is more damaging than acknowledged uncertainty.
Topics
#commitment management#stakeholder communication#false confidence#leadership transparency