CS0-003 · Question #580

CS0-003 Question #580: Real Exam Question with Answer & Explanation

The correct answer is A: Gather all internal stakeholders and review the actions according to the defined incident. Before executing any disaster recovery actions, it is essential to review the incident response and disaster recovery plan with stakeholders. This ensures everyone understands their roles and the process, minimizing errors during the exercise.

Submitted by klara.se· Mar 6, 2026Incident Response and Management

Question

An organization is preparing for a disaster recovery exercise. Which of the following actions should be implemented first?

Options

  • AGather all internal stakeholders and review the actions according to the defined incident
  • BCoordinate the supporting staff for the recovery process to ensure availability at the recovery site.
  • CEnsure that the vendor for the disaster recovery site is scheduled to support the recovery.
  • DIdentify a business-critical system and test by failing over to the disaster recovery location.

Explanation

Before executing any disaster recovery actions, it is essential to review the incident response and disaster recovery plan with stakeholders. This ensures everyone understands their roles and the process, minimizing errors during the exercise.

Topics

#disaster recovery#DR exercise#stakeholder communication#incident planning