Which of the following is the first step that should be performed when establishing a disaster recovery plan?

The correct answer is A. Agree on the goals and objectives of the plan. The first step that should be performed when establishing a disaster recovery plan is to agree on the goals and objectives of the plan. The goals and objectives of the plan should define what the plan aims to achieve, such as minimizing downtime, restoring critical functions…

Submitted by parkjh· Mar 6, 2026Incident Response and Management

Question

Which of the following is the first step that should be performed when establishing a disaster recovery plan?

Options

  • AAgree on the goals and objectives of the plan
  • BDetermine the site to be used during a disaster
  • CDemonstrate adherence to a standard disaster recovery process
  • DIdentify applications to be run during a disaster

How the community answered

(38 responses)
  • A
    92% (35)
  • B
    5% (2)
  • C
    3% (1)

Explanation

The first step that should be performed when establishing a disaster recovery plan is to agree on the goals and objectives of the plan. The goals and objectives of the plan should define what the plan aims to achieve, such as minimizing downtime, restoring critical functions, ensuring data integrity, or meeting compliance requirements. The goals and objectives of the plan should also be aligned with the business needs and priorities of the organization and be measurable and