Which of the following should be updated after a lessons-learned review?

The correct answer is D. Incident response plan. Lessons-Learned Review and Incident Response After a security incident is resolved, a lessons-learned review (also called a post-incident review) is conducted to analyze what happened, what worked, and what needs improvement. The Incident Response Plan (IRP) is the primary…

Submitted by yaw92· Mar 6, 2026Incident Response and Management

Question

Which of the following should be updated after a lessons-learned review?

Options

  • ADisaster recovery plan
  • BBusiness continuity plan
  • CTabletop exercise
  • DIncident response plan

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    3% (1)
  • D
    90% (36)

Explanation

Lessons-Learned Review and Incident Response

After a security incident is resolved, a lessons-learned review (also called a post-incident review) is conducted to analyze what happened, what worked, and what needs improvement. The Incident Response Plan (IRP) is the primary document updated as a result, since it directly governs how incidents are detected, contained, eradicated, and recovered from - and any gaps or inefficiencies discovered should be incorporated to improve future responses.

Why the distractors are wrong:

  • A (Disaster Recovery Plan): The DRP focuses on restoring IT systems and infrastructure after a disaster, not on the step-by-step process of handling security incidents - it is not the primary output of a lessons-learned review.
  • B (Business Continuity Plan): The BCP addresses keeping business operations running during disruptions; while it may occasionally be updated, it is not the standard target of an incident response lessons-learned review.
  • C (Tabletop Exercise): A tabletop exercise is a simulation activity used to test plans, not a document that gets updated as a result of a lessons-learned review.

Memory Tip: Think of the cycle: Incident → Response → Learn → Update the IRP. Lessons learned feed directly back into the plan that governs incident response - keeping the loop closed for continuous improvement.