CRISC · Question #617
Which of the following is a risk practitioner's BEST course of action if a risk assessment identifies a risk that is extremely unlikely but would have a severe impact should it occur?
The correct answer is D. Address the risk by analyzing treatment options. For risks with a severe impact but extremely low likelihood, the best course of action is to analyze treatment options to develop a strategic plan.
Question
Which of the following is a risk practitioner's BEST course of action if a risk assessment identifies a risk that is extremely unlikely but would have a severe impact should it occur?
Options
- ARate the risk as high priority based on the severe impact.
- BObtain management's consent to accept the risk.
- CIgnore the risk due to the extremely low likelihood.
- DAddress the risk by analyzing treatment options.
How the community answered
(21 responses)- A5% (1)
- B5% (1)
- C10% (2)
- D81% (17)
Why each option
For risks with a severe impact but extremely low likelihood, the best course of action is to analyze treatment options to develop a strategic plan.
Rating the risk as high priority based solely on impact might misrepresent its overall risk score if likelihood is extremely low, and it doesn't specify a course of action beyond prioritization.
Obtaining management's consent to accept the risk without first analyzing treatment options might be premature and irresponsible, as there might be cost-effective ways to reduce the impact or likelihood.
Ignoring a risk with severe impact, regardless of likelihood, is irresponsible and a failure of risk management duty, as the organization would be completely unprepared if it materialized.
When a risk has a severe impact, even with an extremely low likelihood, it represents a significant potential threat to the organization. The best course of action is to analyze various treatment options (mitigate, transfer, avoid, accept) to develop a strategic response, ensuring the organization has a plan to manage potential consequences should the unlikely event occur, demonstrating due diligence and preparedness.
Concept tested: Risk response for high impact, low likelihood risks