Which of the following should be of MOST concern to a risk practitioner reviewing an organization risk register after the completion of a series of risk assessments?

Options

  • ASeveral risk action plans have missed target completion dates.
  • BSenior management has accepted more risk than usual.
  • CRisk associated with many assets is only expressed in qualitative terms.
  • DMany risk scenarios are owned by the same senior manager.

Unlock CRISC to see the answer

You've previewed enough free CRISC questions. Unlock CRISC for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Register Review#Risk Action Plans#Risk Treatment Effectiveness#Risk Monitoring