Which of the following is MOST helpful when prioritizing action plans for identified risk?

The correct answer is A. Comparing risk rating against appetite. Prioritizing risk action plans is most effectively guided by comparing the assessed risk rating against the organization's defined risk appetite.

Submitted by lars.no· Apr 18, 2026Risk Response and Reporting

Question

Which of the following is MOST helpful when prioritizing action plans for identified risk?

Options

  • AComparing risk rating against appetite
  • BObtaining input from business units
  • CDetermining cost of controls to mitigate risk
  • DRanking the risk based on likelihood of occurrence

How the community answered

(45 responses)
  • A
    73% (33)
  • B
    16% (7)
  • C
    9% (4)
  • D
    2% (1)

Why each option

Prioritizing risk action plans is most effectively guided by comparing the assessed risk rating against the organization's defined risk appetite.

AComparing risk rating against appetiteCorrect

Risk appetite defines the amount and type of risk an organization is willing to take to achieve its objectives; comparing a risk's current rating (likelihood * impact) against this appetite clearly indicates whether the risk is within acceptable bounds or requires immediate mitigation, thus guiding prioritization. Risks exceeding appetite demand more urgent action than those within it.

BObtaining input from business units

While business unit input is valuable for understanding context and impact, it does not inherently provide a strategic framework for prioritizing risks across the entire organization based on overall acceptable exposure.

CDetermining cost of controls to mitigate risk

The cost of controls is a factor in selecting a specific risk response, but it is not the primary criterion for prioritizing which risks the organization must address first.

DRanking the risk based on likelihood of occurrence

Ranking by likelihood alone is insufficient, as it fails to account for the potential impact of a risk, and both factors must be considered in relation to the organization's overall appetite.

Concept tested: Risk prioritization using risk appetite

Source: https://learn.microsoft.com/en-us/security/benchmark/azure/security-controls-v3-governance-strategy-risk-management#gv-6-perform-risk-assessments-and-reviews

Topics

#Risk Prioritization#Risk Appetite#Risk Response#Risk Rating