Which of the following is MOST important to review when evaluating the ongoing effectiveness of the IT risk register?

The correct answer is B. The status of identified risk scenarios. When evaluating the ongoing effectiveness of an IT risk register, reviewing the status of identified risk scenarios is most important as it directly indicates whether risks are being managed, mitigated, or resolved over time.

Submitted by salim_om· Apr 18, 2026Risk Response and Reporting

Question

Which of the following is MOST important to review when evaluating the ongoing effectiveness of the IT risk register?

Options

  • AThe costs associated with mitigation options
  • BThe status of identified risk scenarios
  • CThe cost-benefit analysis of each risk response
  • DThe timeframes for risk response actions

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    83% (29)
  • C
    3% (1)
  • D
    6% (2)

Why each option

When evaluating the ongoing effectiveness of an IT risk register, reviewing the status of identified risk scenarios is most important as it directly indicates whether risks are being managed, mitigated, or resolved over time.

AThe costs associated with mitigation options

While the costs of mitigation options are important for decision-making, they don't directly reflect the *ongoing effectiveness* of the risk register in tracking and managing the risks themselves.

BThe status of identified risk scenariosCorrect

The ongoing effectiveness of an IT risk register is primarily measured by how well it reflects the current state of risks and supports active risk management. Reviewing the status of identified risk scenarios ensures that risks are being tracked, updated, and addressed, demonstrating whether mitigation efforts are progressing or if new risks have emerged, keeping the register dynamic and relevant.

CThe cost-benefit analysis of each risk response

The cost-benefit analysis is part of the decision process for risk response, not the primary measure of the risk register's ongoing effectiveness as a tracking tool.

DThe timeframes for risk response actions

Timeframes for risk response actions are a component of risk tracking, but the overall "status of identified risk scenarios" encompasses timeframes, assigned owners, and current mitigation progress, making it a more comprehensive measure of effectiveness.

Concept tested: Risk register effectiveness review