Which of the following is a risk practitioner's BEST recommendation to help reduce IT risk associated with scheduling overruns when starting a new application development project?

The correct answer is C. Involve the development team in planning. To reduce the risk of scheduling overruns, a risk practitioner's best recommendation is to involve the development team in the planning process to ensure realistic estimates and commitments.

Submitted by packet_pusher· Apr 18, 2026Risk Response and Reporting

Question

Which of the following is a risk practitioner's BEST recommendation to help reduce IT risk associated with scheduling overruns when starting a new application development project?

Options

  • AImplement a tool to track the development team's deliverables.
  • BReview the software development life cycle.
  • CInvolve the development team in planning.
  • DAssign more developers to the project team.

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    4% (1)
  • C
    70% (16)
  • D
    17% (4)

Why each option

To reduce the risk of scheduling overruns, a risk practitioner's best recommendation is to involve the development team in the planning process to ensure realistic estimates and commitments.

AImplement a tool to track the development team's deliverables.

A tracking tool helps monitor progress but doesn't prevent inaccurate scheduling estimates that lead to overruns.

BReview the software development life cycle.

Reviewing the SDLC might reveal process issues, but it doesn't directly address the accuracy of initial project scheduling estimates.

CInvolve the development team in planning.Correct

Involving the development team directly in the project planning process ensures that estimates for tasks, timelines, and resource requirements are realistic and grounded in the team's actual capabilities and understanding of the technical challenges. This collaborative approach helps create more accurate schedules and increases the team's commitment to meeting those agreed-upon deadlines, significantly reducing the likelihood of scheduling overruns.

DAssign more developers to the project team.

Assigning more developers doesn't guarantee reduced overruns if the initial planning was flawed; it can even introduce more coordination overhead.

Concept tested: Project scheduling risk mitigation