CRISC · Question #3
CRISC Question #3: Real Exam Question with Answer & Explanation
The correct answer is C: maximum tolerable downtime.. Recovery Time Objectives (RTOs) establish the maximum allowable duration a system or process can be down following a disruptive event before unacceptable business impacts occur.
Submitted by kavita_s· Apr 18, 2026Risk Response and Reporting
Question
Recovery the objectives (RTOs) should be based on
Options
- Aminimum tolerable downtime
- Bminimum tolerable loss of data.
- Cmaximum tolerable downtime.
- Dmaximum tolerable loss of data
Explanation
Recovery Time Objectives (RTOs) establish the maximum allowable duration a system or process can be down following a disruptive event before unacceptable business impacts occur.
Common mistakes.
- A. RTO focuses on the maximum tolerable downtime, not the minimum, as businesses aim to operate as long as possible.
- B. Minimum tolerable loss of data relates to the Recovery Point Objective (RPO), which measures the acceptable amount of data loss.
- D. Maximum tolerable loss of data refers to the Recovery Point Objective (RPO), which quantifies the acceptable data loss in terms of time.
Concept tested. Recovery Time Objective (RTO) definition
Topics
#RTO#Recovery Time Objective#Business Continuity Planning#Downtime Tolerance