CRISC · Question #157
Which of the following should be the PRIMARY basis for prioritizing risk responses?
The correct answer is A. The impact of the risk. The primary basis for prioritizing risk responses should be the potential impact of the risk, as it reflects the severity of consequences.
Question
Which of the following should be the PRIMARY basis for prioritizing risk responses?
Options
- AThe impact of the risk
- BThe replacement cost of the business asset
- CThe cost of risk mitigation controls
- DThe classification of the business asset
How the community answered
(37 responses)- A95% (35)
- B3% (1)
- C3% (1)
Why each option
The primary basis for prioritizing risk responses should be the potential impact of the risk, as it reflects the severity of consequences.
Effective risk prioritization requires focusing on risks that could cause the greatest harm to the organization's objectives, assets, or operations. High-impact risks, even if their likelihood is moderate, demand more immediate and comprehensive response strategies to mitigate potential severe consequences.
While the replacement cost contributes to the overall impact, it is only one component; a comprehensive assessment of impact includes financial, operational, reputational, and legal consequences.
The cost of risk mitigation controls is a factor in *selecting* specific responses, but not the primary driver for prioritizing *which* risks to address initially.
Asset classification helps to understand the criticality and sensitivity of an asset, which feeds into the impact assessment, but the classification itself is not the direct basis for prioritizing the risk response.
Concept tested: Risk prioritization factors
Source: https://www.nist.gov/privacy-framework/nist-sp-800-30-rev1-guide-conducting-risk-assessments
Topics
Community Discussion
No community discussion yet for this question.