CRISC · Question #146
Business management is seeking assurance from the CIO that IT has a plan in place for early identification of potential issues that could impact the delivery of a new application Which of the…
The correct answer is D. Include business management on a weekly risk and issues report. To assure business management and enhance successful application delivery, the CIO should ensure regular communication of potential issues by including business management on a weekly risk and issues report.
Question
Business management is seeking assurance from the CIO that IT has a plan in place for early identification of potential issues that could impact the delivery of a new application Which of the following is the BEST way to increase the chances of a successful delivery'?
Options
- AImplement a release and deployment plan
- BConduct comprehensive regression testing.
- CDevelop enterprise-wide key risk indicators (KRls)
- DInclude business management on a weekly risk and issues report
How the community answered
(31 responses)- A10% (3)
- B16% (5)
- C3% (1)
- D71% (22)
Why each option
To assure business management and enhance successful application delivery, the CIO should ensure regular communication of potential issues by including business management on a weekly risk and issues report.
Implementing a release and deployment plan is an important step for execution but does not directly address early identification and communication of *potential issues* to business management during development.
Conducting comprehensive regression testing verifies existing functionality after changes but is a quality assurance activity, not primarily an early warning system for overall project issues to business management.
Developing enterprise-wide key risk indicators (KRIs) is a strategic risk management tool, but a weekly report directly communicates specific project risks and issues relevant to a particular application delivery.
Including business management on a weekly risk and issues report provides them with transparent, timely updates on potential blockers and challenges, enabling early awareness and involvement in resolution. This direct communication fosters trust, demonstrates proactive issue identification, and allows business stakeholders to contribute to decisions that impact successful application delivery.
Concept tested: Project risk communication & stakeholder assurance
Source: https://www.pmi.org/learning/library/risk-management-project-communication-1100