CRE · Question #399
Derating a component to 50 percent of its operating value will generally decrease its failure rate by a factor of:
The correct answer is B. Greater than 30 percent. Derating a component to 50% of its rated operating value exploits the nonlinear relationship between stress and failure rate: failure rate doesn't drop proportionally with stress - it drops more steeply in the mid-stress range, which is why a 50% stress reduction typically…
Question
Derating a component to 50 percent of its operating value will generally decrease its failure rate by a factor of:
Options
- AGreater than 50 percent.
- BGreater than 30 percent.
- CGreater than 10 percent but less than 30 percent.
- DLess than 10 percent.
How the community answered
(27 responses)- A7% (2)
- B78% (21)
- C4% (1)
- D11% (3)
Explanation
Derating a component to 50% of its rated operating value exploits the nonlinear relationship between stress and failure rate: failure rate doesn't drop proportionally with stress - it drops more steeply in the mid-stress range, which is why a 50% stress reduction typically yields a failure rate reduction greater than 30% (roughly in the 30–50% range), making B the best answer.
Why the distractors are wrong:
- A (>50%) overstates the general benefit - while certain specific components under voltage stress can achieve >50% reduction (due to high power-law exponents), as a general rule for a mixed component population, the reduction typically falls short of 50%
- C (10–30%) understates the effect - reliability engineering data (e.g., MIL-HDBK-217) consistently shows derating produces more than a modest 10–30% improvement, since the stress-failure curve is concave
- D (<10%) would make derating practically pointless - in reality it is one of the most cost-effective reliability techniques available
Memory tip: Use the "half-stress, third-less-failure" rule of thumb - derating to 50% buys you more than 30% (roughly a third) fewer failures. The improvement exceeds the intuitive "it should help by the same proportion" expectation because failure rate curves are nonlinear.
Topics
Community Discussion
No community discussion yet for this question.