nerdexam
ASQ

CRE · Question #395

For a reliability plan to be most effective, the reliability tasks should be integrated with which of the following plan?

The correct answer is D. Product design and development. See the full explanation below for the reasoning.

Leadership and Management

Question

For a reliability plan to be most effective, the reliability tasks should be integrated with which of the following plan?

Options

  • AReliability centered maintenance.
  • BProduct sales.
  • CProduct distribution
  • DProduct design and development.

How the community answered

(49 responses)
  • A
    6% (3)
  • B
    12% (6)
  • C
    4% (2)
  • D
    78% (38)

Topics

#reliability planning#design integration#reliability management#product development

Community Discussion

No community discussion yet for this question.

Full CRE Practice