When reliability goals are being developed, reliability predictions are initially used to

The correct answer is B. Estimate potential performance of hardware and software with respect to reliability. See the full explanation below for the reasoning.

Reliability in Design and Development

Question

When reliability goals are being developed, reliability predictions are initially used to

Options

  • ASet goals for all portions of the life cycle of a system.
  • BEstimate potential performance of hardware and software with respect to reliability
  • CMeasure customer needs and provides a means of defining quantitative reliability goals.
  • DEstablish competitive position with respect to reliability

How the community answered

(43 responses)
  • A
    14% (6)
  • B
    72% (31)
  • C
    9% (4)
  • D
    5% (2)