CRE · Question #360

For a company operating multiple units of production equipment, the observed failure rate is 42 x 10-6 failures per operating hour, and the preventive maintenance rate is 320 x 10-6 actions per…

The correct answer is B. 2,762.4 hr. See the full explanation below for the reasoning.

Maintainability and Availability

Question

For a company operating multiple units of production equipment, the observed failure rate is 42 x 10-6 failures per operating hour, and the preventive maintenance rate is 320 x 10-6 actions per hour. What is the mean time between corrective and preventive maintenance (MTBM)?

Options

  • A2,688.2 hr.
  • B2,762.4 hr
  • C2,840.9 hr
  • D26,935.0 hr