On the basis of the fault tree below, what is the likelihood of the top event occurring?
The correct answer is A. 0.0050. You've hit your weekly limit · resets 5am (America/New_York)
Reliability in Design and Development
Question
On the basis of the fault tree below, what is the likelihood of the top event occurring?
Options
- A0.0050
- B0.2600
- C0.3000
- D0.5200
How the community answered
(48 responses)- A83% (40)
- B2% (1)
- C4% (2)
- D10% (5)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#fault tree analysis#top event probability#Boolean logic#system failure