On the basis of the fault tree below, what is the likelihood of the top event occurring?

The correct answer is A. 0.0050. You've hit your weekly limit · resets 5am (America/New_York)

Reliability in Design and Development

Question

On the basis of the fault tree below, what is the likelihood of the top event occurring?

Options

  • A0.0050
  • B0.2600
  • C0.3000
  • D0.5200

How the community answered

(48 responses)
  • A
    83% (40)
  • B
    2% (1)
  • C
    4% (2)
  • D
    10% (5)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#fault tree analysis#top event probability#Boolean logic#system failure