Maintainability engineering is performed for all of the following reasons EXCEPT to

The correct answer is C. Restore equipment to operational condition after failure has occurred. You've hit your weekly limit · resets 5am (America/New_York)

Maintainability and Availability

Question

Maintainability engineering is performed for all of the following reasons EXCEPT to

Options

  • AEstimate the labor hours and other resources required for performing maintenance.
  • BEstimate system availability
  • CRestore equipment to operational condition after failure has occurred
  • DInfluence design to achieve each of maintenance.

How the community answered

(69 responses)
  • A
    9% (6)
  • B
    4% (3)
  • C
    84% (58)
  • D
    3% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#maintainability engineering#design for maintainability#maintenance planning#availability