Which one of the following would NOT be necessary in a corrective action status report?

The correct answer is B. Failure cost. See the full explanation below for the reasoning.

System Reliability

Question

Which one of the following would NOT be necessary in a corrective action status report?

Options

  • ADue date.
  • BFailure cost.
  • CResponsible function (department).
  • DFailure identification.

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    81% (26)
  • C
    6% (2)
  • D
    9% (3)