A pre-award evaluation of a supplier's quality system capability should NOT include consideration of
The correct answer is B. The supplier's geographical location. See the full explanation below for the reasoning.
Product and Process Control
Question
A pre-award evaluation of a supplier's quality system capability should NOT include consideration of
Options
- AThe supplier's product-quality history.
- BThe supplier's geographical location.
- CThe supplier's implementation of quality manual procedures.
- DThe supplier's skills in quality control techniques.
How the community answered
(41 responses)- A2% (1)
- B76% (31)
- C15% (6)
- D7% (3)
Topics
#pre-award evaluation#supplier quality system#supplier capability#supplier selection