Which of the following risk strategy is utilized by both negative and positive risks?
The correct answer is C. Accept. See the full explanation below for the reasoning.
Product and Process Design
Question
Which of the following risk strategy is utilized by both negative and positive risks?
Options
- AShare
- BMitigate
- CAccept
- DTransfer
How the community answered
(56 responses)- A5% (3)
- B9% (5)
- C84% (47)
- D2% (1)
Topics
#risk management#accept strategy#positive risk#negative risk