Which of the following risk strategy is utilized by both negative and positive risks?

The correct answer is C. Accept. See the full explanation below for the reasoning.

Product and Process Design

Question

Which of the following risk strategy is utilized by both negative and positive risks?

Options

  • AShare
  • BMitigate
  • CAccept
  • DTransfer

How the community answered

(56 responses)
  • A
    5% (3)
  • B
    9% (5)
  • C
    84% (47)
  • D
    2% (1)