nerdexam
ASQ

CQE · Question #146

For a process the Cp and Cpk values both turn out to be 2.1. What do you conclude from this?

The correct answer is D. The process is highly capable and centred. See the full explanation below for the reasoning.

Statistical Tools and Techniques

Question

For a process the Cp and Cpk values both turn out to be 2.1. What do you conclude from this?

Options

  • AThe process is capable
  • BThe process is capable but not centred
  • CThe process is not capable
  • DThe process is highly capable and centred

How the community answered

(36 responses)
  • A
    17% (6)
  • B
    8% (3)
  • C
    6% (2)
  • D
    69% (25)

Topics

#process capability#Cp#Cpk#centered process

Community Discussion

No community discussion yet for this question.

Full CQE Practice