For a process the Cp and Cpk values both turn out to be 2.1. What do you conclude from this?
The correct answer is D. The process is highly capable and centred. See the full explanation below for the reasoning.
Statistical Tools and Techniques
Question
For a process the Cp and Cpk values both turn out to be 2.1. What do you conclude from this?
Options
- AThe process is capable
- BThe process is capable but not centred
- CThe process is not capable
- DThe process is highly capable and centred
How the community answered
(36 responses)- A17% (6)
- B8% (3)
- C6% (2)
- D69% (25)
Topics
#process capability#Cp#Cpk#centered process