Isaca
COBIT5 · Question #40
Which of the following MUST be done before an enterprise can determine performance measures for a process improvement initiative?
The correct answer is A. Perform a process risk assessment. See the full explanation below for the reasoning.
Question
Which of the following MUST be done before an enterprise can determine performance measures for a process improvement initiative?
Options
- APerform a process risk assessment
- BCalculate return on investment (ROI)
- CConduct a capabilities assessment
How the community answered
(37 responses)- A78% (29)
- B5% (2)
- C16% (6)
Community Discussion
No community discussion yet for this question.