COBIT5 · Question #24
The level achieved when all processes of a focus area achieve a particular capability level is referred to as:
The correct answer is B. the maturity level. maturity-assessment-using-cobit-2019
Process Capability Assessment Model
Question
The level achieved when all processes of a focus area achieve a particular capability level is referred to as:
Options
- Athe rating level.
- Bthe maturity level.
- Cthe performance level.
How the community answered
(56 responses)- A7% (4)
- B77% (43)
- C16% (9)
Explanation
maturity-assessment-using-cobit-2019
Topics
#maturity level#capability assessment#focus area#process assessment
Community Discussion
No community discussion yet for this question.