Within the COBIT goals cascade, stakeholder drivers are transformed into:
The correct answer is C. the enterprise's actionable strategy. See the full explanation below for the reasoning.
Question
Within the COBIT goals cascade, stakeholder drivers are transformed into:
Options
- Abusiness unit performance metrics
- Bthe enterprise's governance framework
- Cthe enterprise's actionable strategy
How the community answered
(25 responses)- A8% (2)
- B16% (4)
- C76% (19)