In the implementation model, when is IT governance implementation risk BEST managed?
The correct answer is A. Throughout the life cycle. See the full explanation below for the reasoning.
Question
In the implementation model, when is IT governance implementation risk BEST managed?
Options
- AThroughout the life cycle
- BDuring the planning phase
- CJust prior to operationalization
How the community answered
(33 responses)- A76% (25)
- B9% (3)
- C15% (5)