COBIT-2019 · Question #290
Which projects should be included when reporting on performance measurements related to an EGIT implementation program plan?
The correct answer is C. All projects deemed appropriate by IT management. When reporting on performance measurements related to an EGIT implementation program plan, it is important to include all projects that are deemed appropriate by IT management. This is because each project should be evaluated for its ability to provide the desired outcomes and…
Question
Which projects should be included when reporting on performance measurements related to an EGIT implementation program plan?
Options
- AAll projects
- BOnly projects that require corrective action
- CAll projects deemed appropriate by IT management
- DOnly projects that are achieving desired results
How the community answered
(44 responses)- A16% (7)
- B7% (3)
- C73% (32)
- D5% (2)
Explanation
When reporting on performance measurements related to an EGIT implementation program plan, it is important to include all projects that are deemed appropriate by IT management. This is because each project should be evaluated for its ability to provide the desired outcomes and meet the planned objectives, and only projects that have been deemed appropriate should be included in the report. For more information, please refer to the Isaca COBIT 2019 official Manual