An enterprise is not having success implementing IT governance because key staff are not participating in planning meetings. What is the MOST likely underlying cause?
The correct answer is C. Lack of senior leadership commitment. See the full explanation below for the reasoning.
Question
An enterprise is not having success implementing IT governance because key staff are not participating in planning meetings. What is the MOST likely underlying cause?
Options
- ALack of consequences for not attending
- BFailure to utilize program management principles
- CLack of senior leadership commitment
How the community answered
(33 responses)- A9% (3)
- B15% (5)
- C76% (25)