A plan for managing the end of a supplier contract should be created when?

The correct answer is A. The contract is being negotiated. See the full explanation below for the reasoning.

Question

A plan for managing the end of a supplier contract should be created when?

Options

  • AThe contract is being negotiated
  • BThe contract is about to be ended
  • CThe Supplier Manager decides that there is a risk the contract might need to end soon
  • DThe contract has been agreed

How the community answered

(55 responses)
  • A
    80% (44)
  • B
    11% (6)
  • C
    5% (3)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.