CMS7 · Question #379

CMS7 Question #379: Real Exam Question with Answer & Explanation

The correct answer is B. The source of a risk. See the full explanation below for the reasoning.

Question

Which is a definition of a risk cause?

Options

  • AThe impact of a risk on the stage and project tolerance
  • BThe source of a risk
  • CThe overall effect of a risk on the Business Case
  • DHow likely a risk is to occur in a given project situation