What type of improvement should be achieved by using the Deming Cycle?
The correct answer is D. Steady, ongoing improvement. See the full explanation below for the reasoning.
Question
What type of improvement should be achieved by using the Deming Cycle?
Options
- ARapid, one-off improvement
- BReturn on investment within 12 months
- CQuick wins
- DSteady, ongoing improvement
How the community answered
(61 responses)- A3% (2)
- B11% (7)
- C7% (4)
- D79% (48)